Is there a Fall street paving schedule available to see?

We checked with the Carmel Street Department and the answer is yes, there is still paving to go as we head into the fall months. There are three main areas that they are still working on for repaving.

The area around Civic Square:

  • Gradle from 3rd Ave. to Range Line Road.
  • Red Truck Road
  • Around Fire Station 341

Section Two of Brookshire Village:

  • See attached Map Section two is marked with red, while blue is section three to be completed in 2025

Actively finishing up the 96th and Haverstick area:

There will be three smaller strip pave areas to correct smaller issues at the following locations:

  • 116th St in the east bound lane from Haverstick Rd to 4427 E 116th St
  • 106th St in the West bound lane there will be a strip approximately six-feet wide going from Monon trail to Orchard Crossing, this is to repair the road base before it is repaved next year
  • Meeting House Rd from New Market St to Stanhope, this will be curb to curb in this area to replace bad area

Authored by Council Members Tony Green, Adam Aasen, Rich Taylor, Matt Snyder, Jeff Worrell, Teresa Ayers, Shannon Minnaar, Ryan Locke and Anita Joshi.